Preservation / Do I need approval?
Demolition and moving a building
“Demolition” in Newburyport’s ordinances means much less than tearing a building down: a quarter of the walls, or a change to the roofline, is enough. Which board hears it depends on where the building is and what the 1984 survey called it.
Last reviewed against the ordinances September 30, 2026
Or read the part for your area: Fruit Street district · Downtown · Rest of the historic district · Elsewhere in the city
Your building is here
Fruit Street Local Historic District
Fruit Street and a few neighboring lots on High and Prospect Streets, sixteen buildings in all. Its own commission reviews any exterior change seen from the street.
Fruit Street Historic District Commission decides
No demolition permit issues in the district without a certificate. Before any building or demolition permit, you need one of three certificates: of appropriateness (the work suits the district), of non-applicability (nothing reviewable is involved), or of hardship. The Commission decides within 14 days whether the work is reviewable, holds a hearing within 45 days, and decides within 60 days of filing; if it doesn’t act in time, a certificate of hardship issues automatically. It looks only at what can be seen from a public street, park or the river, never at interiors.
Code ch. 16 §16-2; Code ch. 16 §§16-6–16-8; M.G.L. c. 40C
Design guidelines guidance
The 2008 guidelines presume a building stays; a replacement must be approved before the demolition, with documentation and a technical report on the building’s condition.
Code ch. 16 §§16-6–16-8; M.G.L. c. 40C
Historical Commission unclear
Whether the citywide demolition delay also applies inside the Fruit Street district is not settled by either ordinance: chapter 16 requires a certificate before any demolition permit, and the delay ordinance has no carve-out for the district. Ask the Zoning Administrator.
§5-308(A)–(G); ch. 2 §2-103; Zoning §XXVII-C.3 and §XXVIII-C.3 (the carve-outs); Code ch. 16 §§16-6–16-8; M.G.L. c. 40C
Your building is here
Downtown Overlay District (DOD)
The downtown part of the Newburyport Historic District. The Planning Board reviews work on historic buildings and all new construction.
Planning Board decides
Demolition of a historic building downtown, or moving it, needs a Downtown Overlay special permit, granted only on findings that the building has no substantial market value or reasonable use left, with a conditions report and appraisal that can’t be waived. Taking off a historic feature (a cornice, a storefront, a porch) is reviewed too: keep and repair it if reasonably feasible, otherwise replace it in kind. Documentation goes to the Historical Commission at least 30 days before applying.
Zoning §XXVII-D.8, §XXVII-F.7; §XXVIII-D.3, §XXVIII-E.7; Zoning §XXVII-D.5–6; §XXVIII-D.1–2; DCOD demolition diagrams (Apr 8, 2022); Zoning §XXVII-D.3, 7, 9; Zoning §XXVII-C, E, F; §X-H.7–8; Zoning §XXVII-F.4.b–c, F.5.a.iii; ch. 2 §2-104
Historical Commission only if excluded
The demolition delay ordinance doesn’t apply downtown, except to work the Zoning Administrator has excluded from downtown review: a non-historic building 75 or more years old, for example, still goes to the Commission.
§5-308(A)–(G); ch. 2 §2-103; Zoning §XXVII-C.3 and §XXVIII-C.3 (the carve-outs); Zoning §XXVII-C.3, §XXVII-E; §X-H.5
Your building is here
Demolition Control Overlay District (DCOD)
The rest of the Newburyport Historic District, outside downtown and Fruit Street. The Zoning Board reviews major demolition of contributing buildings; the Historical Commission keeps roof changes.
Zoning Board of Appeals decides
For a building that was contributing in 1984 (or is individually listed), removing more than 25% of its exterior walls, counted together since April 2014 and including walls enclosed by additions or openings filled in, or moving it, needs a DCOD special permit before any demolition permit. Demolition is “generally prohibited”: the Board may grant it only on findings that the building has no substantial market value or reasonable use left, taking into account the cost of bringing it up to code. You pay for a conditions report by a preservation professional and an appraisal, and give the Historical Commission photographs, inventory forms and plans at least 21 days before applying; the Commission may report to the Board within 20 days.
Zoning §XXVII-D.8, §XXVII-F.7; §XXVIII-D.3, §XXVIII-E.7; Zoning §XXVII-D.5–6; §XXVIII-D.1–2; DCOD demolition diagrams (Apr 8, 2022); Zoning §XXVIII-E.1–6; special permit criteria §X-H.7; procedure §X-H.8; Zoning §XXVIII-E.4; ch. 2 §2-104
Historical Commission decides whether to delay
Roofline changes stay with the Historical Commission, contributing or not. On a building 75 or more years old (100 for an accessory building), any change to the roofline counts as demolition under the demolition delay ordinance, even if no wall comes down: a change of pitch or ridge, adding or removing a tower or cupola, a dormer that misses the setback rules below, or anything without a roof (a deck, a widow’s walk, a chimney, a railing) that rises above the roof or sits within 3 feet of the edge of a flat roof. Hearing within 30 days; a delay of up to 18 months if the Commission finds the building preferably preserved.
§5-307; Zoning §XXVIII-C.3; art. X
Historical Commission decides whether to delay
For a building not contributing in 1984 the DCOD special permit doesn’t apply; the ordinary demolition delay does. If the building is 75 or more years old (in whole or in part; 100 for a garage, barn or other accessory building), listed on the National Register, or designated by the Commission, the demolition delay ordinance counts as “demolition”: removing or altering more than 25% of its exterior walls, any change to the roofline, moving it on its lot, or moving it off. That work needs a Commission hearing, held within 30 days of a complete application. If the Commission finds the building “preferably preserved” it can delay the demolition permit for up to 18 months; it cannot refuse it outright.
Code of Ordinances ch. 5 art. X §5-307; §5-307; Zoning §XXVIII-C.3, E; art. X
Your building is here
Everywhere else
Outside Fruit Street and the two overlays: most of the city, and a few lots at the edges of the historic district. Only the citywide demolition delay ordinance, for buildings 75 or more years old.
Historical Commission decides whether to delay
If the building is 75 or more years old (in whole or in part; 100 for a garage, barn or other accessory building), listed on the National Register, or designated by the Commission, the demolition delay ordinance counts as “demolition”: removing or altering more than 25% of its exterior walls, any change to the roofline, moving it on its lot, or moving it off. That work needs a Commission hearing, held within 30 days of a complete application. If the Commission finds the building “preferably preserved” it can delay the demolition permit for up to 18 months; it cannot refuse it outright.
Code of Ordinances ch. 5 art. X §5-307; §5-307; §5-308(A)–(G); ch. 2 §2-103; Zoning §XXVII-C.3 and §XXVIII-C.3 (the carve-outs)
Historical Commission how it runs
The Zoning Administrator issues a zoning determination and directs you to file the Commission’s demolition application online, with photographs of every street side, plans of what is to be removed and what will replace it, and a structural engineer’s report if you say the building is unsound. The hearing is noticed to abutters within 300 feet. During a delay you can come back with an amended plan as often as you like; the Commission can release the building early if you have tried in good faith to find a buyer who would keep it, or accept conditions. After the delay you have six months to act on the permit.
§5-308(A); Flowchart; §5-308(A)–(G); ch. 2 §2-103; Zoning §XXVII-C.3 and §XXVIII-C.3 (the carve-outs); §5-308(G); §5-308(G)(3)
Zoning Administrator determines
A part of the building documented as younger than 75 years can be removed without Commission review, on a written determination.
§5-307; §5-307 exclusion (ii)
Wherever the building is
If it happens anyway enforcement
Demolishing without the required approval: in the two overlay districts, no building permit for three years on that lot and any abutting lot under the same ownership; on Fruit Street, fines of up to $300 a day; everywhere, enforcement in court.
§5-310; Zoning §XXVII-F.4.g; §XXVIII-E.8; ch. 16 §16-11
Empty buildings owners must
An unoccupied historic building in either overlay must be kept secure and weathertight: openings closed, roof, walls, chimneys and foundations sound.
Zoning §XXVII-H; §XXVIII-F
Zoning Administrator first stop
Every project starts with a zoning determination. The Zoning Administrator says which of the reviews on this page apply to your building and your plans, and whether the work also needs zoning relief. The site can tell you what the ordinances say; only that determination tells you what applies.
§5-308(A); Flowchart
Holder of a preservation restriction consents
If a preservation restriction is recorded on the property, whatever it covers needs the holder’s consent, on top of everything else here. The City lists the restrictions it holds; the building pages on this site say when the state inventory records one.
M.G.L. c. 184 §§31–33; the recorded restriction
Massachusetts Historical Commission reviews
A project with federal or state money, a federal or state license, or a state permit is reviewed by the Massachusetts Historical Commission for its effect on historic properties, with the local commission consulted. The trigger is the funding or the permit, not the City’s ordinances.
36 CFR 800; M.G.L. c. 9 §§26–27C
Repair first